Dutton’s plan to build nuclear plants on former coal sites not as easy as it seems

By Bianca Hall

Experts have cast doubt on the central pillar of Peter Dutton’s nuclear pitch to voters, saying it would take decades to fill in coal mine voids and make contaminated power station sites safe, during which time fragile and valuable transmission lines would be left to deteriorate.

Operators at several of the seven sites identified by the Coalition for nuclear plants already have well-advanced plans to transform their sites into renewable energy hubs with grid-scale batteries, hydrogen and solar once the coal runs out.

Announcing a future Coalition government would build seven nuclear power stations on the sites of existing coal-fired power stations, Dutton said nuclear facilities could be built on the sites of retired coal power plants using existing transmission poles and wires.

“Each of these locations offer important technical attributes needed for a zero-emissions nuclear plant, including cooling water capacity and transmission infrastructure,” he said.

“That is, we can use the existing poles and wires.”

Dr Katherine Woodthorpe, president of the Australian Academy of Technological Sciences and Engineering, said overseas examples like the United Kingdom’s Hinkley Point C showed it could take decades to approve and build new nuclear facilities – leaving aside the time needed to remediate dirty and geologically unstable former mine sites.

Dr Katherine Woodthorpe said it would be impractical for nuclear facilities to use existing poles and wires.

Dr Katherine Woodthorpe said it would be impractical for nuclear facilities to use existing poles and wires.Credit: Louie Douvis

Woodthorpe said even if it only took 25 years to get a new nuclear facility up and running, that meant the existing transmission potential could lie dormant for 25 years after a coal plant closed.

“In theory it could be done, but when you look at the actual practicality of doing it they’d pretty well have to replace it all,” she said.

Advertisement

University of Sydney professor Glenn Platt, who specialises in energy policy, markets and grids, said there was already high demand for dormant transmission networks among renewables operators.

“The unknown bit [about the Coalition policy] is what happens to those poles and wires between now and when somebody wants to build the nuclear plant, because everybody else is trying to use those poles and wires today for wind and solar and battery projects,” he said.

Dr Glenn Platt with the Evergen intelligent home energy management system at the company’s research headquarters at CSIRO Energy centre, Newcastle.

Dr Glenn Platt with the Evergen intelligent home energy management system at the company’s research headquarters at CSIRO Energy centre, Newcastle.

“The landowners many of these sites are already deploying wind and solar or batteries on those sites. They would use up the available poles and wire infrastructure.”

AGL, which owns the Liddell Power Plant in the Hunter Valley, and Loy Yang A in the Latrobe Valley, said it was well-advanced in plans to transform the sites into industrial energy hubs with renewables, batteries and associated industries.

A spokesman referred this masthead to a statement made by chief executive Damien Nicks in March.

“AGL is already developing our coal and gas power station sites into low-emissions industrial energy hubs,” he said.

An artist’s impression of AGL’s $750m Liddell battery that will be built at the site of its old coal power station in NSW’s Hunter Valley.

An artist’s impression of AGL’s $750m Liddell battery that will be built at the site of its old coal power station in NSW’s Hunter Valley.

“As the owner of these sites, nuclear energy is not a part of these plans. There is no viable schedule for the regulation or development of nuclear energy in Australia, and the cost, build time and public opinion are all prohibitive.”

Many observers are looking to now-closed mine sites for clues about how Dutton’s policy could work on a practical level.

French energy giant Engie, which is rehabilitating Victoria’s closed coal mine Hazelwood, has estimated it could take up to 35 years under a worst-case scenario to finish filling the enormous mine void to a maximum depth of 116m and surface area of 1145 hectares.

Engie Australia and New Zealand manager of environment and planning Adam Moran, who has led the rehabilitation, said a nuclear facility could in theory be put on the site of a former coal power station.

Adam Moran is leading Engie Australia and New Zealand’s rehabilitation of the Hazelwood mine.

Adam Moran is leading Engie Australia and New Zealand’s rehabilitation of the Hazelwood mine.Credit: Justin McManus

“Could it be done? Yes, but if you had to choose a location, would you choose next to a mine void that’s been rehabilitated and full of water, or would you put it some distance further away?” he said.

“You would probably err on the side of caution, and move it well outside of the geological buffer zone that would exist around a rehabilitated coal mine.”

At Hazelwood, which had a 1600-megawatt transmission capacity when the coal mine operated, operators have installed a 150-megawatt-hour battery, which is now plugged into the mine’s existing transmission network.

Loading

In November, Yancoal announced plans to transform the coal mine at Stratford in the Hunter Valley, slated for closure this year, into a major 330-megawatt solar farm and pumped hydro facility capable of producing 300 megawatts in a 12-hour period.

A spokesman for EnergyAustralia, which operates the Mt Piper mine in Lithgow, said the company spoke regularly with governments and regulators.

“To date, we have not discussed the use of any EnergyAustralia sites in the context of nuclear,” he said.

With its Mt Piper plant due to close in 2040, and Yallourn this decade, EnergyAustralia is increasingly looking to diversify, he said.

Loading

“We are focused on continuing to roll out existing, readily available technologies,” he said, which included gas and batteries.

“We are developing more batteries in multiple states, pumped hydro at Lake Lyell in Lithgow and working with partners to underpin further renewable energy.”

The Australian Manufacturing Workers’ Union and Climate Action Network Australia commissioned a report identifying industry and workforce opportunities presented by the renewable energy shift.

National secretary Steve Murphy said with government backing, coal workers could retrain and reap the benefits of renewable technologies.

“This is coming, so let’s get involved and get the best results for our members,” he said.

“We’re in a global race for the jobs of the future, and we spent 10 years standing still, [but] we can catch up very quickly with the natural advantages that we’ve got, provided that there is government support.”